Click on any image to enlarge.
If you know the SmartJob™ where you would like to add, or revise Offset, Min Wait, or Max Wait between Tasks of a SmartJob™, you can search using either Global or Gantt Search. (see Global Search, Gantt Search articles)
1. From the Gantt/Schedule Board click on any Task of the SmartJob™
a. Click on the icon to bring up the details dialog.
2. From Global Search
a. Click on the appropriate SmartJob™ to bring up the details dialog.
3. Click on the SmartJob™ level in the left panel. The General details tab for that SmartJob™ is now displayed.
a. Click on the “Dependencies” tab
4. The Dependency screen will visually display all the dependencies for the SmartJob.
a. Click on the task you would like to revise.
b. You can then click on the icon for opening the dependency details.
5. Clicking on the “Manage Dependencies” icon will bring up a new screen that shows all the details.
a. To add an offset between tasks click on “Method and Offset”
b. And select “Unit to Unit”
6. You will then need to input the number of units that you would like to offset, which allows the engine to schedule the tasks with this “overlap”.
7. To add a Min or Max Wait you will need to click on the “lock” icon.
8. This will bring up a dialog for Min and Max Wait
a. First you will need to slide the “Lock for all successors”
b. And you can select “Method and Offset” of “Finish to Start” or “Start to Start”
c. Then you can slide either “Min Wait”, or “Max Wait”, or both
d. And either use the default value/s
e. Or enter you own value/s
Whichever options you choose you will then need to “Save” your changes.