Click on any image to enlarge.
If you know the SmartJob™ where you would like to revise the Attribute of a Task, you can search using either Global or Gantt Search. (see Global Search, Gantt Search articles)
1. From the Gantt/Schedule Board click on any Task of the SmartJob™
a. Click on the icon to bring up the details dialog.
2. From Global Search
a. Click on the appropriate SmartJob to bring up the details dialog.
3. Click on the SmartJob™ level in the left panel. The General details tab for that SmartJob™ is now displayed.
a. Click on the “Resource Requirements” tab
4. Select the task whose requirements you would like to change
a. You can expand each time segment to view current requirements
b. Click on the edit icon to change the requirements of each time segment
5. The “Edit Resource Requirement” dialog will open
a. Select a specific time segment, or “All Time Segments”
b. The Type and Class of resource if you would like that change
c. The number of resources needed
d. And then the Attribute
e. Value
f. Comparator
g. And Level
h. Finally select the Method to be used (Auto, Pinned or Preferred)
i. And if appropriate, the resource (Pinned or Preferred)
j. From either the Qualified drop down or All resources
k. And Click “Done”
6. If you would like to add an attribute, then click on the Plus icon
a. Which adds another row that you then select the appropriate Attribute settings.
“Save” to commit your changes
Caution: if no attribute is defined, this Task cannot be scheduled.