Click on any image to enlarge.


  1. Filter for the “class” and specific resource to locate the task you wish to start.

  2. Note that Task op status must be listed as “READY”

  3. Click on the start icon or the ellipsis to open the Start dialog

  4. If the date and time is “current” for the activity, and the correct resource is selected, click “start” from the lower right-hand corner of the window.

  5. If you wish to edit the start time to a time and date in the “past”, drop down the calendar and adjust the “date and time” for the start

  6. If you wish to “change” the resource that the task is truly being/was started on, click the edit icon.  Then make the change in the Edit Resource dialog box and click Confirm

  7. Click “Start” from the lower right-hand corner of the window