Click on any image to enlarge.

1.  Select a “Started” or “Partial Complete” task on the Gantt and single click

  1. Click on the details icon to bring up the Task Details

2.  Click on the Execution tab

  1. Either click on the default “Next Action” icon

  2. Or the ellipsis to open the Action Dialog

3.  The Action Dialog will open with some information about the task selected

  1. Enter a time and date for the action, or use the default current time

  2. Enter the total quantity, or time that has been completed

  3. Enter a Discrepant Quantity that will be equal to, or less than the total quantity completed

  4. Enter a non-compliance Reason Code from the drop down

4.  Select a Pause or Completion Method from the drop-down menu

  1. And Complete the action